MONTHLY CONSTRUCTION REPORT
DISTRICT 02 AS OF MAY 11, 1988 PAGE 10
* * * PD * CONTRACT * AMOUNT THIS *TOTAL ESTIMATE* % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * NO * AMOUNT * ESTIMATE * TO DATE * COMP *
************************************************************************************************************************************
PALO PINTO AT LAKE CREEK, 2.0 MI N OF FM 3137 ' .369 '2508'$ 248,797.00'$ .00'$ .00' .0
FM 919,' ,
1178-01-019 ' III
CRP 88(575)S CONSTRUCT BRIDGE AND APPROACHES ' I'
WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 ' ' ********************************************'
DATE WORK COMPLETED- ' ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 60 ADD'L DAYS GRANTED- ' ' '* TIME OF THIS RUN. *'
NORKING DAYS CHARGED- PERCENT TIME USED- ' '********************************************'
JORDAN PAVING CORPORATION, ,
CONTRACT 05880052 ' TOTALS ' '$ 248,797.00'$ .00'$ .00' .0
************************************************************************************************************************************
PARKER FM 51 AT FM 920 & E 4TH ST ' .001 '2020'$ 40,652.00'$ .00'$ .00' .0
FM 51 INMWEATHERFORD ' ' ' '
0313-02-033 ' ' I'I,
MC 313-2-33 FULL TRAFFIC ACTUATED SIGNAL ' ' '
NORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 ' '********************************************'
DATE NORK COMPLETED- ' ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 30 ADD'L DAYS GRANTED- ' * TIME OF THIS RUN. *'
NORKING DAYS CHARGED- PERCENT TIME USED- ' '********************************************'
SIG-OP SYSTEMS, INC.
CONTRACT 02880009 ' TOTALS ' '$ 40,652.00'$ .00'$ .00' .0
************************************************************************************************************************************
PARKER RAMP L AT SH 171, E ' 1.884 '1754'$ 2,347,889.81'$ 55,599.41'$ 193,240.16' 8.6
IH 20 TONNCREEK ' I '' '
0314-07-021, , ,
IR 20-4(203)408 , ' , '
NORK ORDER- 01-27-88 NORK BEGAN- 03-03-88
DATE NORK COMPLETED-
CONTRACT WORKING DAYS- 270 ADD'L DAYS GRANTED- 1
WORKING DAYS CHARGED- 44 PERCENT TIME USED- 16 ''
SOUTHWESTERN CONTRACTING COMPANY
CONTRACT 12870006 ' TOTALS ' '$ 2,347,889.81'$ 55,599.41'$ 193,240.16' 8.0
************************************************************************************************************************************
SOMERVELL 0.4 MI S OF PLUXY RV ' 5.787 '2039'$ 874,470.95'$ 48,733.41'$ 49,509.07' 5.9
SH 144 BOSQUE CO LINE
0386-01-020
CSR 386-1-20 ACP OVERLAY AND NIDEN STRUCTURES' '''
NORK ORDER- 03-08-88 NORK BEGAN- 03-28-88
DATE NORK COMPLETED-
CONTRACT WORKING DAYS- 140 ADD'L DAYS GRANTED- 1'
WORKING DAYS CHARGED- 23 PERCENT TIME USED- 16
DONNING BROS., INC.
CONTRACT 02880027 ' TOTALS ' '$ 874,470.95'$ 48,733.41'$ 49,509.07' 5.0
************************************************************************************************************************************
SOMERVELL ERATH CO LINE ' 17.365 '2293'$ 822,591.44'$ .00'$ .00' .0
US 67 FM 56 IN GLEN R OSE
0259-02-034
CPM 259-2-34 ACP LEVEL-UP,PLANT MIX SEAL AND
NORK ORDER- 00-00-00 NORK BEGAN- 00-00-00 ' ' '********************************************
DATE NORK COMPLETED- ' ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 45 ADD'L DAYS GRANTED- ' '* TIME OF THIS RUN.
NORKING DAYS CHARGED- PERCENT TIME USED- ' '********************************************'
ZACK BURKETT CO. ' ' ' ' '
CONTRACT 03880108 ' TOTALS ' '$ 822,591.44'$ .00'$ .00' .0
************************************************************************************************************************************
SOMERVELL NORTH END OF FM 199, SOUTHEAST ' 4.622 '2380'$ 928,475.32'$ .00'$ .00' .0
FM 199 US 67 ' ' ,
0778-01-015 ' , ''r
CSR 778-1-15 WIDEN GRA,STRS,BASE AND 2 CRSE SURF ' '''
WORK ORDER- 05-05-88 NORK BEGAN- 00-00-00 ' '********************************************'
DATE NORK COMPLETED- ' 1 '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 125 ADD'L DAYS GRANTED- '* TIME OF THIS RUN. *'
NORKING DAYS CHARGED- PERCENT TIME USED- ' ' '********************************************'
BROWN & BLAKNEY, INC.
CONTRACT 04880070 ' TOTALS ' '$ 928,475.32'$ .00'$ .00' .0
************************************************************************************************************************************
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. State Department of Highways and Public Transportation. Construction Division. Texas Construction Report: May 1988, report, May 1, 1988; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1031941/m1/16/: accessed July 11, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.