MONTHLY CONSTRUCTION REPORT
DISTRICT 04 AS OF MAY 11, 1988 PAGE 35
* * * PD * CONTRACT * AMOUNT THIS *TOTAL ESTIMATE* % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * NO * AMOUNT * ESTIMATE * TO DATE * COMP *
************************************************************************************************************************************
POTTER IH 40, N & N ' 9.911 '1938'$ 1,953,677.30'$ 40,539.34'$ 151,185.61' 8.2
LP 335 US 287 IN AMARI LLO
2635-01-018
CSR 2635-1-18 ACP REHAB
WORK ORDER- 02-10-88 NORK BEGAN- 03-14-88
DATE WORK COMPLETED-
CONTRACT WORKING DAYS- 120 ADD'L DAYS GRANTED-
WORKING DAYS CHARGED- 38 PERCENT TIME USED- 32
J. LEE MILLIGAN, INC.
CONTRACT 01880029 ' TOTALS ' '$ 1,953,677.30'$ 40,539.34'$ 151,185.61' 8.0
POTTER RANDALL C/L ' 6.024 '2048'$ 3,772,762.70'$ 164,963.80'$ 779,300.30' 21.8
LP 335 IH 40, E OF AMA RILLO
2635-01-016
C 2635-1-16 GRADING, STRUCTURES AND SURFACING
WORK ORDER- 02-25-88 WORK BEGAN- 03-14-88
DATE WORK COMPLETED-
CONTRACT WORKING DAYS- 275 ADD'L DAYS GRANTED-
WORKING DAYS CHARGED- 28 PERCENT TIME USED- 10
OLMOS EQUIPMENT COMPANY, INC. ' ' '
CONTRACT 02880036 ' TOTALS ' '$ 3,772,762.70'$ 164,963.80'$ 779,300.30' 21.0
POTTER 0.1 MI N OF BELL ST ' 5.700 '2116'$ 183,800.00'$ 31,799.89'$ 31,799.89' 18.2
IH 40 GRAND ST (EXCL IH 27 I/C)
0275-01-101
CL 275-1-101 LANDSCAPE DEVELOPMENT
WORK ORDER- 03-21-88 WORK BEGAN- 04-04-88
DATE WORK COMPLETED-
CONTRACT WORKING DAYS- 60 ADD'L DAYS GRANTED-
WORKING DAYS CHARGED- 16 PERCENT TIME USED- 27
SHAFFORD'S LANDSCAPE, INC.
CONTRACT 02880072 ' TOTALS ' '$ 183,800.00'$ 31,799.89'$ 31,799.89' 18.0
POTTER AMARILLO CR ' 30.751 '0795'$ 1,086,626.20'$ 1,900.00'$ 1,036,380.05' 99.9
US 287 CANADIAN RV BR
0041-05-037
CSB 41-5-37 RESURFACE ASPHALTIC CONCRETE
DALLAM SHERMAN C/L ' 15.006 '0796'$ 428,918.16$ 224,012.76'$ 257,832.76' 63.2
US 287 OKLAHOMA STATE LINE ,06601-01
0066-01-010 ,
CD 66-1-10 RESURFACE ASPHALTIC CONCRETE
WORK ORDER- 04-13-87 WORK BEGAN- 07-27-87
DATE WORK COMPLETED-
CONTRACT WORKING DAYS- 100 ADD'L DAYS GRANTED-
WORKING DAYS CHARGED- 79 PERCENT TIME USED- 79
J. LEE MILLIGAN, INC.
CONTRACT 03870021 ' TOTALS ' '$ 1,515,544.36'$ 225,912.76'$ 1,294,212.81' 89.0
POTTER IN AMARILLO FR 0.2 MI E OF SONCY RD, E ' 2.695 '2485'$ 514,924.29'$ .00'$ .00' .0
IH 40 ATTEBURY RD (IN
0275-01-105 SECTIONS)
MC 275-1-105 FLY ASH TREAT EXIST BS, PRIME & 2
WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 ' '********************************************'
DATE WORK COMPLETED- ' ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 60 ADD'L DAYS GRANTED- ' ' '* TIME OF THIS RUN.
WORKING DAYS CHARGED- PERCENT TIME USED- ' ' ********************************************'
L. A. FULLER & SONS CONSTRUCTION,
INC.
CONTRACT 05880029 ' TOTALS ' '$ 514,924.29'$ .00'$ .00' .0
POTTER AT NE 24TH,THOMPSON ' .167 '2487'$ 169,450.00'$ .00'$ .00' .0
US 87 PK,HASTINGS,CENTRAL,WILLOW CRK,CHER RY &
0041-07-066 ST FRANCES_ST
CSBH 41-7-66 CONCRETE REPAIR & EPOXY
WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 ' '********************************************'
DATE WORK COMPLETED- ' ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 100 ADD'L DAYS GRANTED- ' ' '* TIME OF THIS RUN. *'
WORKING DAYS CHARGED- PERCENT TIME USED- ' ' '********************************************'
OLMOS EQUIPMENT COMPANY, INC.
CONTRACT 05880031 ' TOTALS ' '$ 169,450.00'$ .00'$ .00' .0
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. State Department of Highways and Public Transportation. Construction Division. Texas Construction Report: May 1988, report, May 1, 1988; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1031941/m1/41/: accessed July 11, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.