DISTRICT 12 AS OF DEC 08, 1992 PAGE 73
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION *LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
HARRIS AT BERRY BAYOU ' .023 ' $ 761,866.03'$ 22,105.07'$ 526,069.79' 72.8'
SH 3
0051-02-064
CC 51-2-64 REPLACE BRIDGE
WORK ORDER- 01-28-92 WORK BEGAN- 02-26-92
DATE WORK COMPLETED- TIME COMPUTED 02-13-92
CONTRACT WORKING DAYS- 120 ADDL DAYS GRANTED-
WORKING DAYS CHARGED- 119 PERCENT TIME USED- 99
AUSTIN BRIDGE & ROAD, INC.
CONTRACT 10910063 'TOTALS ' 761,866.03' 22,105.07' 526,069.79' 72.8'
HARRIS VARIOUS LOCATIONS IN HARRIS COUNTY ' .001 ' $ 880,413.15'$ .00'$ 812,932.11' 97.1'
VA
3912-71-329
NC 912-71-329 SEALING, PAV REPAIR & BR REPAIR
4ORK ORDER- 11-14-91 WORK BEGAN- 01-08-92
DATE WORK COMPLETED- TIME COMPUTED 11-30-91 ' '
CONTRACT WORKING DAYS- 120 ADDL DAYS GRANTED-
WORKING DAYS CHARGED- 118 PERCENT TIME USED- 98
UNIVERSAL SERVICES CO., INC.
CONTRACT 10910070 'TOTALS ' 880,413.15' .00' 812,932.11' 97.1'
HARRIS AT WORTHAM BLVD ' .002 ' $ 148,326.90'$ .00'$ .00' .0'
M 1960
L685-01-067
MC 1685-1-67 TRAF SIGNAL W/SFTY LTG
WORK ORDER- 11-12-92 MORK BEGAN- 00-00-00' ' ************************************************'
DATE WORK COMPLETED- TIME COMPUTED 12-13-92 ' ' * NO CURRENT ESTIMATE PROCESSED AT THE
CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- ' ' * TIME OF THIS RUN *
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 ' '************************************************'
PFEIFFER & SON, INC.
CONTRACT 10920009 'TOTALS ' 148,326.90' .00' .00' 0.0'
HARRIS IN HOUSTON BTWN REED RD & AIRPORT BLVD ' .465 ' $ 603,938.00'$ .00'$ .00' .0'
SH 288
0598-01-051
NH 92(146)R RELOC SB EXIT RAMP
WORK ORDER- 12-03-92 WORK BEGAN- 00-00-00 ' '************************************************
DATE WORK COMPLETED- TIME COMPUTED 12-19-92 ' ' * NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 45 ADDL DAYS GRANTED- ' ' * TIME OF THIS RUN *'
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 ' ************************************************'
BROWN & ROOT, INC.
CONTRACT 10920013 'TOTALS ' 603,938.00' .00' .00' 0.0'
************************************************************************************************************************************
HARRIS E OF SILBER DRIVE IH 45' 6.070 ' $ 747,380.00'$ .00'$ .00' .0'
1H 10 (IN SECTIONS)
0271-07-207
IM 10-7(348)762 CONCRETE PAVEMENT REPAIR
WORK ORDER- 11-06-92 WORK BEGAN- 00-00-00
DATE WORK COMPLETED- TIME COMPUTED 11-22-92
CONTRACT WORKING DAYS- 150 ADDL DAYS GRANTED-
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0
UNIVERSAL SERVICES CO., INC.
CONTRACT 10920042 'TOTALS ' 747,380.00' .00' .00' 0.0'
************************************************************************************************************************************
HARRIS N OF JFK BLVD ' 1.910 ' $ 30,424,382.99'$ .00'$ 29,889,325.89' 99.9'
BW 8 E OF JFK BLVD ' ' ' '
3256-02-027 '
F 1126(4) MN LN U/P
WORK ORDER- 12-30-88 WORK BEGAN- 01-15-89 ' '************************************************'
DATE WORK COMPLETED- TIME COMPUTED 01-15-89 ' ' * NO CURRENT ESTIMATE PROCESSED AT THE
CONTRACT WORKING DAYS- 390 ADDL DAYS GRANTED- 38 ' ' * TIME OF THIS RUN
WORKING DAYS CHARGED- 581 PERCENT TIME USED- 136 ' ************************************************'
TRAYLOR BROS., INC.
CONTRACT 11880001 'TOTALS ' 30,424,382.99' .00' 29,889,325.89' 99.9'
************************************************************************************************************************************4
MIS.CIS.19
MONTHLY CONSTRUCTION REPORT
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction and Contract Administration Division. Texas Construction Report: December 1992, report, December 1, 1992; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1032397/m1/79/: accessed August 15, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.