MIS.CIS.19 MONTHLY CONSTRUCTION REPORT
DISTRICT 09 AS OF JAN 09, 1998 PAGE 70
** ************************************************ xe****+**********************+*******************x ************ *****
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
BELL AT MISSOURI PACIFIC RR IN TEMPLE ' .284 ' 1,815,109.65' 66,905.86' 1,614,955.57' 93.6'
SH 53 ' ' '
0232-01-033
STP 96(13)R CONSTRUCT RAILROAD SEPARATION ' ' ' '
NORK ORDER- 09-11-96 NORK BEGAN- 09-27-96
DATE NORK COMPLETED- TIME COMPUTED- 09-27-96
CONTRACT WORKING DAYS- 195 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 175 PERCENT TIME USED- 90
GAREY CONSTRUCTION COMPANY, INC. ' ' ' '
JAY-REESE CONTRACTORS, INC. ' ' ' '
CONTRACT 07963025 ' TOTALS ' 1,815,109.65' 66,905.86' 1,614,955.57' 93.6'
************************************************************************************************************************************
BELL FT HOOD STREET E 0.119 MI ' .237 ' 687,809.13' 45,318.81' 118,513.55' 18.1'
FM 439
0836-03-042
STP 97(388)R GR, STRS & SURF
NORK ORDER- 10-10-97 NORK BEGAN- 11-11-97
DATE NORK COMPLETED- TIME COMPUTED- 10-26-97
CONTRACT WORKING DAYS- 180 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 17 PERCENT TIME USED- 9
ODELL GEER CONSTRUCTION COMPANY, INC.
CONTRACT 08973094 ' TOTALS ' 687,809.13' 45,318.81' 118,513.55' 18.1'
BOSQUE 1.8 MI E OF MORGAN ' 1.037 ' 1,049,645.90' 3,462.15' 1,013,951.27' 99.6'
FM 927 3.6 MI E OF MORGAN AT STEELE CR
0779-04-017
STP 95(232)R CONSTR BR & APPRS
NORK ORDER- 08-21-96 NORK BEGAN- 09-06-96
DATE NORK COMPLETED- TIME COMPUTED- 09-06-96
CONTRACT WORKING DAYS- 135 ADDL DAYS GRANTED- 9
WORKING DAYS CHARGED- 155 PERCENT TIME USED- 108
ELLIS-MCGINNIS CONSTRUCTION CO. ' ' '
CONTRACT 07963026 ' TOTALS ' 1,049,645.90' 3,462.15' 1,013,951.27' 99.6'
************************************************************************************************************************************
CORYELL @ CORYELL CREEK ' .620 ' 1,044,378.60' 66,667.42' 415,807.44' 41.9'
US 84
0055-06-026
BR 97(314) REPL BR & APPR
NORK ORDER- 07-18-97 NORK BEGAN- 08-29-97
DATE NORK COMPLETED- TIME COMPUTED- 08-03-97
CONTRACT WORKING DAYS- 150 ADDL DAYS GRANTED- 10
WORKING DAYS CHARGED- 32 PERCENT TIME USED- 20
ELLIS-MCGINNIS CONSTRUCTION CO.
CONTRACT 06973028 ' TOTALS ' 1,044,378.60' 66,667.42' 415,807.44' 41.9'
************************************************************************************************************************************
CORYELL @ 6TH ST & @ LOVERS LANE IN ' .002 ' 265,560.55' 35,507.77' 192,369.00' 76.2'
US 84 GATESVILLE
0055-05-043
C 55-5-43 SIGNS, SIGNALS & PVMT MRKNGS
NORK ORDER- 07-10-97 NORK BEGAN- 09-23-97
DATE NORK COMPLETED- TIME COMPUTED- 10-09-97
CONTRACT WORKING DAYS- 90 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 43 PERCENT TIME USED- 48
G. CARTER CONSTRUCTION COMPANY, INC.
CONTRACT 06973077 ' TOTALS ' 265,560.55' 35,507.77' 192,369.00' 76.2'
HAMILTON COMANCHE CL ' 15.167 ' 1,247,917.56' 145,160.64' 1,341,274.01' 99.9'
SH 36 N HAMILTON CITY LIMITS
0183-02-022
CSR 183-2-22 SEAL, OVLY & SFTY END TREATMENTS
NORK ORDER- 07-30-97 WORK BEGAN- 08-28-97
DATE NORK COMPLETED- TIME COMPUTED- 08-15-97
CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 2
WORKING DAYS CHARGED- 61 PERCENT TIME USED- 98
BAY MAINTENANCE COMPANY, INC.
CONTRACT .06973110 ' TOTALS ' 1,247,917.56' 145,160.64' 1,341,274.01' 99.9'
************************************************************************************************************************************4
4q
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction and Maintenance Division. Texas Construction and Maintenance Report: January 1988, report, January 1, 1998; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1032426/m1/78/: accessed July 11, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.