MIS.CIS.19 MONTHLY STATE LET CONSTRUCTION REPORT
DISTRICT 01 AS OF APR 08, 1999 PAGE 11
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
RED RIVER 3RD STREET IN CLARKSVILLE ' 35.093 ' 4,089,649.48' 306,902.53' 3,443,969.31' 88.6'
FM 909 CR 419''' '
0189-03-026 '''
CSR 189-3-26 REHABILITATION OF EXISTING ROADWAY '' '
NORK ORDER- 04-17-97 NORK BEGAN- 05-12-97 ' '''
DATE NORK COMPLETED- TIME COMPUTED- 05-03-97 '''
CONTRACT WORKING DAYS- 340 ADDL DAYS GRANTED- 99 '''
WORKING DAYS CHARGED- 317 PERCENT TIME USED- 72 '''
HARTFORD FIRE INSURANCE COMPANY ''''
CONTRACT 03973049 ' TOTALS ' 4,089,649.48' 306,902.53' 3,443,969.31' 88.6'
RED RIVER CLARKSVILLE ' 28.687 ' 2,559,854.30' .00' 3,235,212.53' 99.9'
US 82 BONIE C/L '''
0046-01-053 ''''
CSR 46-1-53 OVERLAY'''
NORK ORDER- 04-17-98 NORK BEGAN- 05-04-98 ''''
DATE NORK COMPLETED- TIME COMPUTED- 05-03-98 '''
CONTRACT NORKING DAYS- 76 ADDL DAYS GRANTED- 55 ''''
WORKING DAYS CHARGED- 109 PERCENT TIME USED- 83 '''
BUSTER PAVING CO., INC.'''''
CONTRACT 03983003 ' TOTALS ' 2,559,854.30' .00' 3,235,212.53' 99.9'
RED RIVER FM 411 ' 15.920 ' 2,549,085.84' 335,379.22' 354,126.52' 14.6'
FM 41O US 271''''
0722-02-027' ''
STP 99(4)R REHAB EXISTING 2 LANE FAC''
NORK ORDER- 12-11-98 NORK BEGAN- 01-29-99 ''''
DATE NORK COMPLETED- TIME COMPUTED- 12-27-98 '''
CONTRACT NORKING DAYS- 128 ADDL DAYS GRANTED- 0 '' ''
WORKING DAYS CHARGED- 12 PERCENT TIME USED- 9 ''''
NES SCOTT, INC.'II
CONTRACT 11983019 ' TOTALS ' 2,549,085.84' 335,379.22' 354,126.52' 14.6'
RED RIVER US 82 ' .100 ' 111,653.67' 9,208.82' 21,292.90' 20.0'
US 82 AT SH 37''''
0045-12-063'''
STP 99(86)HES MISCELLANEOUS NORK''
NORK ORDER- 01-08-99 NORK BEGAN- 02-22-99 ''
DATE NORK COMPLETED- TIME COMPUTED- 02-22-99 ''''
CONTRACT NORKING DAYS- 30 ADDL DAYS GRANTED- 3 ''''
NORKING DAYS CHARGED- 11 PERCENT TIME USED- 33 ''''
T L S TRAFFIC CONTROLS, INC.''' '
CONTRACT 12983044 ' TOTALS ' 111,653.67' 9,208.82' 21,292.90' 20.0'
DISTRICT CONTRACT AMOUNT 174,645,740.20
DISTRICT ESTIMATES THIS MONTH 8,906,113.06
DISTRICT TOTAL ESTIMATES PAID TO DATE 95,768,600.90
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: April 1999, report, April 1, 1999; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1033507/m1/15/: accessed July 11, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.