MIS.CIS.19
DISTRICT 02MONTHLY STATE LET CONSTRUCTION REPORT
AS OF APR 08, 1999PAGE 20
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
ERATH AT SOUTH FORK OF NORTH BOSQUE RIVER ' .926 ' 1,197,928.05' 58.25' 1,122,246.53' 98.6'
SH 108 .
0343-04-034 '''
BR 98(102) REPLACE BRIDGE AND APPROACHES''''
NORK ORDER- 04-22-98 NORK BEGAN- 05-11-98 '' '
DATE NORK COMPLETED- TIME COMPUTED- 05-08-98 ' '''
CONTRACT WORKING DAYS- 144 ADDL DAYS GRANTED- 4 '' '
WORKING DAYS CHARGED- 148 PERCENT TIME USED- 100 ''''
ELLIS-MCGINNIS CONSTRUCTION CO.
CONTRACT 02983067 ' TOTALS ' 1,197,928.05' 58.25' 1,122,246.53' 98.6'
ERATH FM 913 ' 33.640 ' 934,200.97' .00' .00' .0'
US 67 SOMERVELL COUNTY LINE'''
0259-01-029 '''
CPM 259-1-29 OVERLAY'' '
WORK ORDER- 04-06-99 WORK BEGAN- 00-00-00 **************************
DATE NORK COMPLETED- TIME COMPUTED- 00-00-00 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 30 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN*
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 ''* ** ******* ** ******* ******
PEACHTREE CONSTRUCTION, INC. '''
CONTRACT 02993050 ' TOTALS ' 934,200.97' .00' .00' 0.0'
ERATH ETC FM 1188/1189 INTERSECTION BU ' 189.900 ' 2,194,299.67' .00' .00' .0'
US 281 ETC 377J IN STEPHENVILLE''''
0250-03-037 ETC '''
CPM 250-3-37 SEAL COAT''''
WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 ''**** ****** ** ******** **** *
DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 49 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN*
WORK ING DAY S CHARGED- 0 PERCENT T IME USED- 0 ''**** ***** *** ************ *
CSS, INC.'' '
CONTRACT 02993103 ' TOTALS ' 2,194,299.67' .00' .00' 0.0'
ERATH NCL OF DUBLIN ' 9.083 ' 16,255,308.45' .00' 5,834,051.71' 40.6'
US 67 FM 988' ''
0079-05-033'''
NH 98(174) RECONST 2 LANE TO 4 LANE DIVIDED' ''
WORK ORDER- 08-19-98 WORK BEGAN- 08-20-98 ''* *** ***** ****************
DATE NORK COMPLETED- TIME COMPUTED- 09-04-98 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 680 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN *
WORKING DAYS CHARGED- 145 PERCENT TIME USED- 21 ' '*************************
JAY MILLS CONTRACTING, INCORPORATED '
CONTRACT 06983064 ' TOTALS ' 16,255,308.45' .00' 5,834,051.71' 40.6'
HOOD AT BRAZOS RIVER ' 1.103 ' 3,975,530.69' 374,404.16' 2,113,293.98' 55.9'
FM 51'''
0313-08-022 '''
BR 98(132) REPLACE BRIDGE'' '
NORK ORDER- 08-31-98 NORK BEGAN- 09-14-98 ''''
DATE WORK COMPLETED- TIME COMPUTED- 09-16-98 ''''
CONTRACT NORKING DAYS- 294 ADDL DAYS GRANTED- 0 ' ''
WORKING DAYS CHARGED- 113 PERCENT TIME USED- 38 ''''
CONCHO CONSTRUCTION COMPANY, INC.'''
CONTRACT 06983086 ' TOTALS ' 3,975,530.69' 374,404.16' 2,113,293.98' 55.9'
JACK ETC 4.97 KM SOUTH OF FM 1191 ' 55.480 ' 644,551.37' .00' .00' .0'
US 281 ETC ARCHER COUNTY LINE''''
0249-05-024 ETC' ''
CPM 249-5-24 SEAL COAT' ''
WORK ORDER- 03-23-99 WORK BEGAN- 00-00-00 ''**** ***************** *** *
DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 45 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN*
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 ''*** ************ ** **** *** *
JOE RICHARDS, INC.'''
CONTRACT 02993053 ' TOTALS ' 644,551.37' .00' .00' 0.0'5'
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: April 1999, report, April 1, 1999; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1033507/m1/24/: accessed July 11, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.