MIS.CIS.19 MONTHLY STATE LET CONSTRUCTION REPORT
DISTRICT 01 AS OF JUL 10, 2000 PAGE 3
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
GRAYSON N OF US 69 ' 2.937 ' 7,538,790.90' 64,946.48' 4,157,007.44' 58.0'
US 82 FANNIN C/L
0045-19-015
C 45-19-15 GR, STRS, BASE & SURF
WORK ORDER- 09-03-98 WORK BEGAN- 09-23-98
DATE MORK COMPLETED- TIME COMPUTED- 09-19-98
CONTRACT WORKING DAYS- 274 ADDL DAYS GRANTED- 57
W WORKING DAYS CHARGED- 74 PERCENT TIME USED- 22
RUSHING PAVING COMPANY ' t
CONTRACT 07983003 ' TOTALS ' 7,538,790.90' 64,946.48' 4,157,007.44' 58.0'
************************************************************************************************************************************
GRAYSON US 69 AT ' .310 ' 280,436.30' 1,900.00' 254,765.84' 98.6'
US 69 ETC CRAWFORD ST IN DENISON
.0047-02-112 ETC
STP 99(353)HES MISCELLANEOUS WORK
WORK ORDER- 08-19-99 WORK BEGAN- 11-30-99
DATE WORK COMPLETED- TIME COMPUTED- 09-04-99
CONTRACT WORKING DAYS- 75 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 93 PERCENT TIME USED- 124
INTEGRATED ROADWAY SERVICES, INC.
CONTRACT 07993069 ' TOTALS ' 280,436.30' 1,900.00' 254,765.84' 98.6'
************************************************************************************************************************************
GRAYSON AT SAND CREEK ' .928 ' 1,500,223.13' 126,647.25' 722,434.59' 50.6'
SH 56
0045-03-023
BR 99(13) REPLACE BRIDGE AND APPROACHES
WORK ORDER- 09-24-99 WORK BEGAN- 11-04-99
DATE MORK COMPLETED- TIME COMPUTED- 10-10-99
CONTRACT WORKING DAYS- 180 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 92 PERCENT TIME USED- 51
RUSHING PAVING COMPANY
CONTRACT 08993030 ' TOTALS ' 1,500,223.13' 126,647.25' 722,434.59' 50.6'
************************************************************************************************************************************
GRAYSON 1.625 KM N OF ELM STREET ' 8.803 ' 3,326,762.86' 133,410.49' 2,447,760.03' 77.4'
SH 289 FM 902
0091-01-029
STP 99(433)RM GR, LIME TR SUB, BS, STRS & SURF
WORK ORDER- 09-16-99 WORK BEGAN- 09-23-99
DATE WORK COMPLETED- TIME COMPUTED- 10-02-99
CONTRACT WORKING DAYS- 300 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 127 PERCENT TIME USED- 42
D. L. LENNON INCORPORATED - CONTRACTOR
CONTRACT 08993086 ' TOTALS ' 3,326,762.86' 133,410.49' 2,447,760.03' 77.4'
************************************************************************************************************************************
GRAYSON @ UNION PACIFIC RAILROAD (WESTBOUND) ' 3.438 ' 2,926,549.43' 231,994.19' 1,887,836.65' 67.9'
FM 120
0728-01-031
BR 99(536) REPLACE EXISTING BRIDGE &
APPROACHES
WORK ORDER- 09-24-99 WORK BEGAN- 10-22-99
DATE WORK COMPLETED- TIME COMPUTED- 10-10-99
CONTRACT WORKING DAYS- 225 ADDL DAYS GRANTED- 54
WORKING DAYS CHARGED- 148 PERCENT TIME USED- 53
RUSHING PAVING COMPANY
CONTRACT 08993089 ' TOTALS ' 2,926,549.43' 231,994.19' 1,887,836.65' 67.9'
***********************************************************************************************************************************
GRAYSON @ CHOCTAW CREEK ' 1.342 ' 1,820,791.24' 57,158.62' 1,179,489.30' 68.1'
FM 1753 .
0316-03-006
BR 99(414) REPL BRIDGE & REHAB BRIDGE
WORK ORDER- 10-19-99 WORK BEGAN- 11-16-99
DATE WORK COMPLETED- TIME COMPUTED- 11-04-99
CONTRACT WORKING DAYS- 285 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 103 PERCENT TIME USED- 36
SWATSELL CONTRACTING, INC.
CONTRACT 09993049 ' TOTALS ' 1,820,791.24' 57,158.62' 1,179,489.30' 68.1'
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/11/: accessed July 11, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.