DISTRICT 12 AS OF JUL 10, 2000 PAGE 195
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
GALVESTON IH 45 ' 3.471 ' 8,565,373.87' 200,198.14' 8,254,565.16' 99.9'
SH 6 T.C.T.R.R.
0192-04-081
C 192-4-81 CONSTR BERM, LIFT STA & RAISE RDWY
NORK ORDER- 12-08-98 WORK BEGAN- 03-05-99
DATE WORK COMPLETED- TIME COMPUTED- 12-24-98
y CONTRACT WORKING DAYS- 195 ADDL DAYS GRANTED- 75
WORKING DAYS CHARGED- 274 PERCENT TIME USED- 101
J. D. ABRAMS, INC.
CONTRACT 10983034 ' TOTALS ' 8,565,373.87' 200,198.14' 8,254,565.16' 99.9'
************************************************************************************************************************************
GALVESTON S END CLEAR CREEK BRIDGE ' 3.744 ' 10,973,537.09' 601,005.78' 3,239,163.58' 30.7'
FM 270 FM 518
A 3312-02-004
STP 2000(22)MM GR, BASE, CONC PVMT & WDN STRS
WORK ORDER- 01-14-00 WORK BEGAN- 02-08-00
DATE WORK COMPLETED- TIME COMPUTED- 01-30-00
CONTRACT WORKING DAYS- 312 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 91 PERCENT TIME USED- 29
TEXAS-STERLING CONSTRUCTION INC.
CONTRACT 10993002 ' TOTALS ' 10,973,537.09' 601,005.78' 3,239,163.58' 30.7'
************************************************************************************************************************************
GALVESTON SEANALL BLVD. ' 1.116 ' 29,644.50' .00' 16,498.85' 58.5'
SH 87 GALVESTON FERRY LANDING
0367-06-052
CPM 367-6-52 BS REP & CR SL
GALVESTON SH 6 ' 8.101 ' 291,250.00' 49,455.10' 336,654.92' 99.9'
IH 45 FM 1764
0500-04-098
CPM 500-4-98 BS REP & JT REP
WORK ORDER- 01-03-00 WORK BEGAN- 01-21-00
DATE WORK COMPLETED- TIME COMPUTED- 01-19-00
CONTRACT WORKING DAYS- 45 ADDL DAYS GRANTED- 15
WORKING DAYS CHARGED- 44 PERCENT TIME USED- 73
INFRASTRUCTURE SERVICES, INC.
CONTRACT 11993042 ' TOTALS ' 320,894.50' 49,455.10' 353,153.77' 99.9'
************************************************************************************************************************************
GALVESTON COLLEGE OF THE MAINLAND IN N TEXAS CITY ' 9.330 ' 1,329,438.39' 131,057.11' 1,126,705.22' 89.2'
VA BAY STREET PARK IN EAST TEXAS CITY
0912-73-058
STP 97(221)TE TEXAS CITY TRAILS PHASE II
WORK ORDER- 01-06-00 WORK BEGAN- 02-24-00
DATE WORK COMPLETED- TIME COMPUTED- 01-22-00
CONTRACT WORKING DAYS- 84 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 84 PERCENT TIME USED- 100
HUBCO, INC.
CONTRACT 11993064 ' TOTALS ' 1,329,438.39' 131,057.11' 1,126,705.22' 89.2'
************************************************************************************************************************************
GCLVESTON CLEARVIEW AVENUE ' .002 ' 131,437.45' 19,452.23' 127,641.44' 99.9'
FM 518 IN FRIENDSWOOD
0976-03-081
C 976-3-81 TRAFFIC SIGNAL
WORK ORDER- 01-05-00 WORK BEGAN- 02-21-00
DATE WORK COMPLETED- TIME COMPUTED- 01-21-00
.CONTRACT WORKING DAYS- 58 ADDL DAYS GRANTED- 11
WORKING DAYS CHARGED- 69 PERCENT TIME USED- 100
HUBCO, INC.
CONTRACT 12993014 ' TOTALS ' 131,437.45' 19,452.23' 127,641.44' 99.9'
************************************************************************************************************************************
GALVESTON ENTRANCE TO SANTA FE HIGH SCHOOL ' .002 ' 173,910.00' 23,869.23' 161,774.26' 97.9'
SH 6 IN SANTA FE
0192-04-085
C 192-4-85 TRAFFIC SIGNAL
WORK ORDER- 01-03-00 WORK BEGAN- 03-29-00
DATE WORK COMPLETED- TIME COMPUTED- 01-19-00
CONTRACT WORKING DAYS- 75 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 73 PERCENT TIME USED- 97
TRAF-TEX, INC.
CONTRACT 12993056 ' TOTALS ' 173,910.00' 23,869.23' 161,774.26' 97.9'MIS. CIS. 19
MONTHLY STATE LET CONSTRUCTION REPORT
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/203/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.