DISTRICT 12 AS OF JUL 10, 2000 PAGE 208
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
HARRIS 11TH ST ' 4.864 ' 3,155,374.36' 156,845.06' 2,892,104.23' 96.4'
VA S. OF PINEMONT
0912-71-436
STP 94(215)TE TRANSPORTATION ENHANCEMENT
MORK ORDER- 01-27-99 MORK BEGAN- 02-15-99
DATE WORK COMPLETED- TIME COMPUTED- 02-12-99 '
CONTRACT WORKING DAYS- 190 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 190 PERCENT TIME USED- 100
CONTINENTAL CONSTRUCTION, INC.
CONTRACT 10983039 ' TOTALS ' 3,155,374.36' 156,845.06' 2,892,104.23' 96.4'
HARRIS US 59 (SOUTH) ' 5.000 ' 778,378.10' 70,719.07' 835,079.54' 99.9'
IH 610 US 290
0271-17-130
IM 610-7(372) FULL DEPTH CONCRETE REPAIR
WORK ORDER- 11-23-99 MORK BEGAN- 01-11-00
DATE MORK COMPLETED- TIME COMPUTED- 12-09-99
CONTRACT WORKING DAYS- 240 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 175 PERCENT TIME USED- 73
KINSEL INDUSTRIES, INC.
CONTRACT 10993010 ' TOTALS ' 778,378.10' 70,719.07' 835,079.54' 99.9'
************************************************************************************************************************************
HARRIS AT THREE LAKES BOULEVARD / ' .003 ' 420,888.33' 1,632.00' 231,572.43' 57.3'
SH 249 CANYON GATES
0720-03-107
C 720-3-107 TRAFFIC SIGNAL
WORK ORDER- 12-01-99 WORK BEGAN- 01-06-00
DATE WORK COMPLETED- TIME COMPUTED- 12-17-99
CONTRACT WORKING DAYS- 130 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 73 PERCENT TIME USED- 56
FLORIDA TRAFFIC CONTROL DEVICES, INC.
CONTRACT 10993012 ' TOTALS ' 420,888.33' 1,632.00' 231,572.43' 57.3'
************************************************************************************************************************************
HARRIS ON-STREET NETWORK THROUGH-OUT N HOUSTON ' 27.800 ' 1,170,345.15' 45,956.02' 494,278.22' 43.9'
VA AND BIKEWAYS ALONG OLD KATY ROAD
0912-71-502
CM 96(729) BIKE N HOUSTON ON - ST BIKEWAY
PHASE 1
WORK ORDER- 12-06-99 WORK BEGAN- 02-17-00
DATE WORK COMPLETED- TIME COMPUTED- 12-22-99
CONTRACT WORKING DAYS- 123 ADDL DAYS GRANTED- 14
WORKING DAYS CHARGED- 105 PERCENT TIME USED- 77
HUBCO, INC.
CONTRACT 10993054 ' TOTALS ' 1,170,345.15' 45,956.02' 494,278.22' 43.9'
HARRIS W/I HERMAN BROWN PARK TO: DUNVEGAN MAY' 2.550 ' 616,910.04' 81,127.65' 558,847.34' 95.3'
VA AT MERCURY DRIVE & WESTSHIRE AT IH 10
0912-71-506
CM 96(733) BIKE & HIKE TRL TRHOUGH HERMAN
BROWN PRK
WORK ORDER- 02-12-99 WORK BEGAN- 03-15-99
DATE NORK COMPLETED- TIME COMPUTED- 02-28-99
CONTRACT WORKING DAYS- 130 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 121 PERCENT TIME USED- 93
INFRASTRUCTURE SERVICES, INC.'
CONTRACT 11983025 ' TOTALS ' 616,910.04' 81,127.65' 558,847.34' 95.3'
************************************************************************************************************************************
HARRIS 1.0 MI NORTH OF SH 146 ' 1.228 ' 8,951,353.55' 29,985.70' 4,462,847.06' 52.4'
SP 330 SH 146
0508-07-277
C 508-7-277 CONST 0/P, FR RD, AND RP
HARRIS SH 146 ' .962 ' 8,786,880.16' -29,979.62' 6,897,069.31' 82.6'
SP 330 1.0 MI NORTH OF SH 146
0508-07-278
CM 98(492) GR, STRS, BASE, PAVEMENT
WORK ORDER- 11-30-98 WORK BEGAN- 11-30-98
DATE WORK COMPLETED- TIME COMPUTED- 12-16-98
CONTRACT WORKING DAYS- 338 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 90 PERCENT TIME USED- 27
MILLIAMS BROTHERS CONSTRUCTION CO., INC.
CONTRACT 11983045 ' TOTALS ' 17,738,233.71' 6.08' 11,359,916.37' 67.4'
************************************************************************************************************************************MONTHLY STATE LET CONSTRUCTION REPORT
MIS.CIS.19
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/216/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.