DISTRICT 12 AS OF JUL 10, 2000 PAGE 211
***************************>***********************************************x****c********>**** *****************************>**
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
MONTGOMERY LP 336 M ' .604 ' 1,097,749.99' .00' .00' .0'
SH 105 WILSON ROAD
0338-03-081
CSR 338-3-81 ADD C&G N/ STM SWR
WORK ORDER- 04-18-00 MORK BEGAN- 00-00-00
DATE WORK COMPLETED- TIME COMPUTED- 05-04-00
CONTRACT WORKING DAYS- 92 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0
HUBCO, INC.
CONTRACT 03003086 ' TOTALS ' 1,097,749.99' .00' .00' 0.0'
MONTGOMERY ETC FM 1774 IH' 42.555 ' 4,648,457.15' .00' .00' .0'
FM 1488 ETC 45, ETC.
a 0523-10-022 ETC '
STP 2000(463)R BS REP, CR SL, ACP 0/L & PV MARKS
WORK ORDER- 05-09-00 WORK BEGAN- 00-00-00
DATE WORK COMPLETED- TIME COMPUTED- 05-25-00
CONTRACT WORKING DAYS- 210 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 21 PERCENT TIME USED- 10
HUBCO, INC.
CONTRACT 04003004 ' TOTALS ' 4,648,457.15' .00' .00' 0.0'
************************************************************************************************************************************
MONTGOMERY FM 3083 LP ' 84.010 ' 1,296,518.89' .00' .00' .0'
SH 75 ETC 336 (S), ETC.
0110-03-045 ETC
STP 2000(489)R RESTORATION OF EXISTING ROAD
WORK ORDER- 06-12-00 WORK BEGAN- 00-00-00
DATE WORK COMPLETED- TIME COMPUTED- 06-28-00
CONTRACT WORKING DAYS- 221 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 3 PERCENT TIME USED- 1
SCR CONSTRUCTION CO., INC.
CONTRACT 05003081 ' TOTALS ' 1,296,518.89' .00' .00' 0.0'
************************************************************************************************************************************
MONTGOMERY 0.318 MI S OF TAMINA RD ' 4.392 ' 41,735,182.90' 464,584.92' 20,363,053.28' 51.3'
IH 45 0.100 MI N OF FM 1488
0110-04-141
NH 98(426) WDN GR, STRS & SURF
MONTGOMERY 0.318 MI S OF TAMINA ' .121 ' 3,010,793.45' 149,063.46' 463,998.87' 16.2'
IH 45 0.100 MI N OF FM 1488
0110-04-165
CM 98(427) GR, STR & HOV LN
WORK ORDER- 08-17-98 WORK BEGAN- 08-19-98
DATE WORK COMPLETED- TIME COMPUTED- 09-02-98
CONTRACT WORKING DAYS- 896 ADDL DAYS GRANTED- 83
WORKING DAYS CHARGED- 496 PERCENT TIME USED- 51
HILLIAMS BROTHERS CONSTRUCTION CO., INC.
CONTRACT 07983064 ' TOTALS ' 44,745,976.35' 613,648.38' 20,827,052.15' 48.9'
************************************************************************************************************************************
MONTGOMERY WALDEN RD FROM SH 105 ' 4.271 ' 5,510,916.37' 47,399.96' 5,344,264.24' 99.9'
CS WALDEN ON LAKE CONROE SUBDIV
0912-37-087
STP 95(328)RM HID 2 TO 4 LNS UNDIV
WORK ORDER- 12-07-98 WORK BEGAN- 01-12-99
DATE WORK COMPLETED- TIME COMPUTED- 12-23-98
CONTRACT WORKING DAYS- 230 ADDL DAYS GRANTED- 32
'*ORKING DAYS CHARGED- 261 PERCENT TIME USED- 100
KINSEL INDUSTRIES, INC.
CONTRACT 10983038 ' TOTALS ' 5,510,916.37' 47,399.96' 5,344,264.24' 99.9'
************************************************************************************************************************************
MONTGOMERY ENTRANCE TO SPLENDORA FIRE DEPARTMENT ' .004 ' 377,356.80' 127,625.41' 324,493.57' 89.5'
BU 59-L IN SPLENDORA
0177-16-005
C 177-16-5 TRAFFIC SIGNAL
WORK ORDER- 12-03-99 WORK BEGAN- 12-21-99
DATE WORK COMPLETED- TIME COMPUTED- 12-19-99
CONTRACT WORKING DAYS- 108 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 106 PERCENT TIME USED- 98
STATEWIDE TRAFFIC SIGNAL COMPANY
CONTRACT 11993014 ' TOTALS ' 377,356.80' 127,625.41' 324,493.57' 89.5'MIS. CIS. 19
MONTHLY STATE LET CONSTRUCTION REPORT
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/219/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.