Texas Construction and Maintenance Report: July 2000 Page: PAGE222
508 p. ; 28 cm.View a full description of this report.
Extracted Text
The following text was automatically extracted from the image on this page using optical character recognition software:
MIS.CIS.19
DISTRICT 12MONTHLY LOCAL LET MAINTENANCE REPORT
AS OF JUL 10, 2000PAGE 222
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
BRAZORIA VARIOUS HWYS IN S. BRAZORIA COUNTY ' 1.000 ' 51,030.00' .00' 42,894.01' 84.0'
SH0035 VARIOUS HWYS IN S. BRAZORIA COUNTY ' ' ' '
6026-61-001 ' ' ' '
RMC - 602661001 REFLECTIVE PAVEMENT MARKINGS
WORK ORDER- 08-21-98 WORK BEGAN- 08-31-98
DATE WORK COMPLETED- TIME COMPUTED- 09-01-98
CONTRACT WORKING DAYS- 730 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 669 PERCENT TIME USED- 92
9 , , Y 1
SAFETY LIGHTS SALES AND LEASING, INC. OF TEXAS
CONTRACT 04981205 ' TOTALS ' 51,030.00' .00' 42,894.01' 84.0'
************************************************************************************************************************************
BRAZORIA VARIOUS HWYS IN S. BRAZORIA COUNTY ' 1.000 ' 94,974.00' .00' 86,112.60' 90.6'
SH0035 VARIOUS HWYS IN S. BRAZORIA COUNTY
6041-95-001
RMC - 604195001 ASPHALT CONCRETE TY D SURFACE
OVERLAY
WORK ORDER- 07-27-99 WORK BEGAN- 02-07-00
DATE WORK COMPLETED- TIME COMPUTED- 08-02-99
CONTRACT WORKING DAYS- 730 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 334 PERCENT TIME USED- 46
EL DORADO PAVING COMPANY, INC.
CONTRACT 04991211 ' TOTALS ' 94,974.00' .00' 86,112.60' 90.6'
************************************************************************************************************************************
BRAZORIA SH 332 AT INTRACOASTAL WATERWAY-SURFSIDE' 1.000 ' 72,250.00' .00' .00' 99.9'
SH0332 SH 332 AT INTRACOASTAL WATERWAY-SURFSIDE'
6055-81-001
RMC - 605581001 ATTENUATOR INSTALLATIONS
, I
WORK ORDER- 06-07-00 MORK BEGAN- 06-12-00 ' '**************************************************
DATE WORK COMPLETED- TIME COMPUTED- 06-12-00 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 30 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN
WORKING DAYS CHARGED- 15 PERCENT TIME USED- 50 ' '**************************************************
KINSEL INDUSTRIES, INC.
CONTRACT 05001208 ' TOTALS ' 72,250.00' .00' .00' 99.9'
************************************************************************************************************************************
BRAZORIA VARIOUS HWYS. IN N. BRAZORIA COUNTY ' 1.000 ' 47,775.00' 7,461.00' 23,244.00' 48.6'
SH0035 VARIOUS HWYS. IN N. BRAZORIA COUNTY
6036-80-001
RMC - 603680001 STORM SEWER SYSTEM CLEANING
WORK ORDER- 02-17-00 WORK BEGAN- 03-01-00
DATE WORK COMPLETED- TIME COMPUTED- 03-01-00
CONTRACT WORKING DAYS- 365 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 122 PERCENT TIME USED- 33
SHE-CO., INC., OF HOUSTON, HARRIS COUNTY, TEXAS
CONTRACT 11991201 ' TOTALS ' 47,775.00' 7,461.00' 23,244.00' 48.6'
************************************************************************************************************************************
FORT BEND VARIOUS HWYS IN FORT BEND COUNTY ' .001 ' 178,821.00' .00' 142,551.79'100.0'
U50059 VARIOUS HWYS IN FORT BEND COUNTY
6051-61-001
RMC - 605161001 ASPHALT PAVEMENT REPAIR
WORK ORDER- 03-01-00 WORK BEGAN- 03-27-00 ' '**************************************************
DATE WORK COMPLETED- 06-27-00 TIME COMPUTED- 03-27-00 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 365 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN
WORKING DAYS CHARGED- 79 PERCENT TIME USED- 22 ' '**************************************************
FORDE CONSTRUCTION COMPANY, INC.
CONTRACT 01001208 ' TOTALS ' 178,821.00' .00' 142,551.79'100.0'
************************************************************************************************************************************
FORT BEND VARIOUS HWYS IN FORT BEND COUNTY ' .001 ' 74,160.00' .00' 67,109.35' 90.4'
US0059 VARIOUS HWYS IN FORT BEND COUNTY
6037-96-001
RMC - 603796001 FULL DEPTH CONCRETE REPAIR
WORK ORDER- 01-01-00 WORK BEGAN- 04-27-00
DATE WORK COMPLETED- TIME COMPUTED- 01-24-00
CONTRACT WORKING DAYS- 365 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 159 PERCENT TIME USED- 44
1 ! , , ,
INFRASTRUCTURE SERVICES, INC.
CONTRACT 01991208 ' TOTALS ' 74,160.00' .00' 67,109.35' 90.4'
************************************************************************************************************************************
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/230/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.