Texas Construction and Maintenance Report: July 2000 Page: PAGE241
508 p. ; 28 cm.View a full description of this report.
Extracted Text
The following text was automatically extracted from the image on this page using optical character recognition software:
MIS.CIS.19MONTHLY STATE LET CONSTRUCTION REPORT
DISTRICT 13 AS OF JUL 10, 2000 PAGE 241
******** >************************>*****xx***>k~**********************K*********~****** * *****> ************ l* x ****
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
WHARTON 0.5 MI N. OF US 59 ' 1.000 ' 260,971.70' 16,506.34' 90,612.96' 36.1'
BU 59-R . 0.5 MI S. OF US 59
0089-10-015
CL 89-10-15 LANDSCAPE DEVELOPMENT
NORK ORDER- 02-25-00 NORK BEGAN- 03-28-00 -
DATE WORK COMPLETED- TIME COMPUTED- 03-12-00
* CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 53 PERCENT TIME USED- 88
HAMILTON MOWING
CONTRACT 01003048 ' TOTALS ' 260,971.70' 16,506.34' 90,612.96' 36.1'
WHARTON ETC LP 525 S. OF EL CAMPO 0.18 ' 23.718 ' 3,129,635.22' .00' .00' .0'
US 59 ETC MI. S. OF LP 523 N. OF LOUISE
* 0089-06-069 ETC
CPM 89-6-69 ACP OVERLAY
NORK ORDER- 04-17-00 WORK BEGAN- 05-01-00
'DATE NORK COMPLETED- TIME COMPUTED- 05-01-00
CONTRACT WORKING DAYS- 60 -ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0
HUNTER INDUSTRIES, INC.
CONTRACT 03003058 ' TOTALS ' 3,129,635.22' .00' .00' 0.0'
WHARTON 1.3 MI S OF PEACH CREEK ' 1.710 ' 5,048,426.48' .00' .00' .0'
BU 59-R FM 1301
0089-10-002
MG 2000(82) GR, STRS, SURF, ADDL LANES
NORK ORDER- 06-12-00 WORK BEGAN- 00-00-00
DATE NORK COMPLETED- TIME COMPUTED- 06-28-00
CONTRACT WORKING DAYS- 240 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0
PATE & PATE ENTERPRISES, INC.
CONTRACT 05003061 ' TOTALS ' 5,048,426.48' .00' .00' 0.0'
************************************************************************************************************************************
NHARTON BU 59-R IN WHARTON ' 1.110 ' 2,977,411.90' 108,642.80' 1,518,002.55' 53.6'
FM 1301 1.1 MI EAST OF BU 59-R
1412-03-029
STP 99(375)R RECONST GR & SURF, C&G AND STORM
SENER
WORK ORDER- 09-20-99 NORK BEGAN- 12-06-99
DATE WORK COMPLETED- TIME COMPUTED- 10-06-99
CONTRACT WORKING DAYS- 175 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 87 PERCENT TIME USED- .50
TEXAS-STERLING CONSTRUCTION INC. -
CONTRACT 08993022 ' TOTALS ' 2,977,411.90' 108,642.80' 1,518,002.55' 53.6'
************************************************************************************************************************************
NHARTON AT NEST MUSTANG CREEK CR 378 ' .076 ' 357,420.14' 78,487.46' 346,621.38' 99.9'
CR (CR 378) STR. AA05-45-001
0913-09-027
BR 98(466)OX REPLACE BRIDGE & APPRS.
MATAGORDA AT IRRIGATION CANAL (DRAM) ' .002 ' 80,485.46' .00' 75,461.07' 98.6'
CR (MCCROSKY ROAD) STR. AA01-42-004
0913-21-028
BR 98(468)OX REPLACE BRIDGE & APPRS.
WORK ORDER- 01-07-00 WORK BEGAN- 01-14-00
DATE WORK COMPLETED- TIME COMPUTED- 01-23-00
CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0
WORKINGG DAYS CHARGED- 55 PERCENT TIME USED- 92
REXCO, INC.
CONTRACT 11993027 ' TOTALS ' 437,905.60' 78,487.46' 422,082.45' 99.9'
NHARTON FM 442 IN BOLING ' .500 ' 63,079.25' .00' .00' .0'
FM 1301 0.5SMI S. OF FM 442
1412-03-031
C 1412-3-31 LANDSCAPE DEVELOPMENT
WORK ORDER- 01-05-00 WORK BEGAN- 00-00-00
DATE WORK COMPLETED- TIME COMPUTED- 01-21-00
CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0
CHC & SONS, INC.
CONTRACT 12993018 ' TOTALS ' 63,079.25' .00' .00' 0.0'
************************************************************************************************************************************
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/249/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.