Texas Construction and Maintenance Report: July 2000 Page: PAGE274
508 p. ; 28 cm.View a full description of this report.
Extracted Text
The following text was automatically extracted from the image on this page using optical character recognition software:
MIS.CIS.19
DISTRICT 14MONTHLY LOCAL LET MAINTENANCE REPORT
AS OF JUL 10, 2000PAGE 274
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
BURNET VARIOUS LOCATIONS IN BURNET COUNTY ' .001 ' 20,604.00' .00' 20,331.00' 98.6'
US0281
6012-44-001
RMC - 601244001 PICNIC AREA MAINTENANCE AND MORNING
NORK ORDER-*. 05-22-97 WORK BEGAN- 06-02-97 ' '**************************************************
DATE WORK COMPLETED- TIME COMPUTED- 06-02-97 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 365 ADDL DAYS.GRANTED- 0 ' '* TIME OF THIS RUN *
WORKING DAYS CHARGED- 365 PERCENT TIME USED- 100 '**************************************************
CAROLYN HALEY
CONTRACT 04971404 ' TOTALS ' 20,604.00' .00' 20,331.00' 98.6'
BURNET NILLIAMSON/BURNET C/L ' 3.026 ' 177,826.15' .00' .00' .0'
US0183 7 MI. NORTH ' ' ' '
6057-53-001
RMC - 605753001 LEVELING OR OVERLAY W/LAYDON
MACHINE -
WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 ''**************************************************
DATE WORK COMPLETED- TIME COMPUTED- 00-00-00 ' '* -NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 15 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 ' '**************************************************
AUSTIN BRIDGE & ROAD, INC.
CONTRACT 06001401 ' TOTALS ' 177,826.15' .00' .00' 0.0'
BURNET - VARIOUS ROADWAYS IN BURNET COUNTY ' .001 ' 56,815.20' .00' 11,311.20' 19.9'
US0281 ' '
6050-89-001',
RMC - 605089001 LITTER PICKUP AND DISPOSAL
WORK ORDER- 03-06-00 WORK BEGAN- 03-14-00 r**************************************************
DATE WORK COMPLETED- TIME COMPUTED- 03-14-00 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 80 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN
WORKING DAYS CHARGED- 13 PERCENT TIME USED- 16 ' '**************************************************
TEXAS TREE & LANDSCAPE '
CONTRACT 12991405 ' TOTALS ' 56,815.20' .00' 11,311.20' 19.9'
************************************************************************************************************************************
CALDELL VARIOUS ROADWAYS IN CALDWELL COUNTY ' .001 ' 257,017.37' .00' 20,825.90' 8.1'
US0183 .
6051-78-001
RMC - 605178001 MOWING HIGHWAY RIGHT OF WAY
WORK ORDER- 03-24-00 WORK BEGAN- 03-24-00 ''**************************************************
DATE WORK COMPLETED- TIME COMPUTED- 03-24-00 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 120 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN *'
WORKING DAYS CHARGED- 7 PERCENT TIME USED- 6 ' '**************************************************'
BRONSBORO ENTERPRISES, INC. -
CONTRACT 02001401 ' TOTALS ' 257,017.37' .00' 20,825.90' 8.1'
CALDWELL VARIOUS LOCATIONS IN ' .001 ' 38,204.50' .00' 35,199.37' 92.1'
US0183 CALDNELL AND BASTROP COUNTIES'
6025-52-001'''
RMC - 602552001 LITTER PICKUP AND DISPOSAL
WORK ORDER- 08-11-98 WORK BEGAN- 08-12-98 ''**************************************************
DATE WORK COMPLETED- TIME COMPUTED- 08-19-98 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 56 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN
WORKING DAYS CHARGED- 29 PERCENT TIME USED- 52 ''**************************************************
AMERICAN PRESSURE WASH & MAINTENANCE, INC.
CONTRACT 02981401 ' TOTALS ' 38,204.50' .00' 35,199.37' 92.1'
************************************************************************************************************************************
CALDWELL VARIOUS LOCATIONS ON ' 9.600 ' 306,685.66' 298,761.91' 298,761.91' 97.4'
US0183 US 183 AND SH 21
6053-25-001
RMC - 605325001 SEAL COAT AND HMACP
LEVEL-UP/OVERLAY
WORK ORDER- 05-12-00 WORKBEGAN- 05-18-00
DATE WORK COMPLETED- TIME COMPUTED- 05-22-00
CONTRACT WORKING DAYS- 16 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 7 PERCENT TIME USED- 44
HUNTER INDUSTRIES, INC. ' '
CONTRACT 03001408 ' TOTALS ' 306,685.66' 298,761.91' 298,761.91' 97.4'
************************************************************************************************************************************I
*************** *************************************************************************
TTTTTTTTTTTTTTTTTTTTTTTT TT TTTT nT r TT TT-s-TTTT -- -- .-.-. .. .-... .. .. .. ._ _ .. __ _ __ __ _ .__
-------- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/282/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.