Texas Construction and Maintenance Report: July 2000 Page: PAGE287
508 p. ; 28 cm.View a full description of this report.
Extracted Text
The following text was automatically extracted from the image on this page using optical character recognition software:
MONTHLY STATE LET CONSTRUCTION REPORT
AS OF JUL 10, 2000PAGE 287
MIS.CIS.19
DISTRICT 15************* *
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
BEXAR IN BEXAR COUNTY ON MONTGOMERY DR ' 3.276 ' 4,545,881.41' 13,381.60' 4,715,985.85' 99.9'
CS FROM WALZEM RD TO GIBBS-SPRAL RD
0915-12-170
STP 97(200)MM GRAD, STR, BASE, SURF, SIGNALS
WORK ORDER- 04-22-97 NORK BEGAN- 07-31-97
DATE NORK COMPLETED- . TIME COMPUTED- 05-08-97
CONTRACT WORKING DAYS- 360 ADDL DAYS GRANTED- 5
WORKING DAYS CHARGED- 518 PERCENT TIME USED- 142
T 1 1 4 t
RAY FARIS, INC.
CONTRACT 03973003 ' TOTALS ' 4,545,881.41' 13,381.60' 4,715,985.85' 99.9'
************************************************************************************************************************************
BEXAR IN SAN ANTONIO ON EVERS RD AT ' .287 ' 428,682.16' .00' .00' .0'
MH NURZBACH RD
* 0915-12-125
STP 98(273)MM GRAD, STR, BASE, SURF, CURB,
TRAFFIC SIG
NORK ORDER- 06-14-00 NORK BEGAN- 00-00-00
DATE NORK-COMPLETED- TIME COMPUTED- 06-30-00
CONTRACT WORKING DAYS- 57 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0
AUSTIN BRIDGE & ROAD, INC.
CONTRACT 04003029 ' TOTALS ' 428,682.16' .00' .00' 0.0'
BEXAR IN SAN ANTONIO ON 24TH STREET ' 1.855 ' 1,804,734.50' 142,801.43' 142,801.43' 8.3'
CS FROM COMMERCE TO CULEBRA RD
0915-12-169
STP 98(265)MM GRAD, STR, BASE, SURF
WORK ORDER- 05-26-00 WORK BEGAN- 06-14-00
DATE NORK COMPLETED- TIME COMPUTED- 06-11-00
CONTRACT WORKING DAYS- 238 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 12 PERCENT TIME USED- 5
BAY MAINTENANCE COMPANY, INC.
CONTRACT 04003060 ' TOTALS ' 1,804,734.50' 142,801.43' 142,801.43' 8.3'
************************************************************************************************************************************
BEXAR 0.554 KM N OF LP 1604 ' .200 ' 2,147,967.47' 9,517.53' 2,047,428.31' 99.9'
US 281 0.754 KM N OF LP 1604
0253-04-108
CD 253-4-108 GRAD, STR, BASE, SURF, SIGNING
WORK ORDER- 06-04-99 NORK BEGAN- 08-04-99
DATE NORK COMPLETED- TIME COMPUTED- 06-20-99
CONTRACT WORKING DAYS- 90 ADDL DAYS GRANTED- 10
WORKING DAYS CHARGED- 124 PERCENT TIME USED- 124
BAY MAINTENANCE COMPANY, INC.
CONTRACT 04993041 ' TOTALS ' 2;147,967.47' 9,517.53' 2,047,428.31' 99.9'
BEXAR IN SAN ANTONIO ON S NEN BRAUNFELS ' 2.227 ' 395,056.47' 11,685.00' 210,889.55' 56.1'
CS FROM RIGSBY TO SOUTHCROSS/IH 37
0915-12-249
STP 98(263)MM REPAIR AND RECONSTRUCT SIDEWALKS
NORK ORDER- 06-17-99 NORK BEGAN- 07-03-99
DATE WORK COMPLETED- TIME COMPUTED- 07-03-99
CONTRACT WORKING DAYS- 134 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 89 PERCENT TIME USED- 66
E-Z BEL CONSTRUCTION COMPANY
CONTRACT 04993087 ' TOTALS ' 395,056.47' 11,685.00' 210,889.55' 56.1'
BEXAR LP 13 ' 4.900 ' 5,164,424.09' .00' .00' .0'
IH 37 1.30MI S OF US 181
0073-08-122
NH 2000(663) TRAFFIC MANAGEMENT SYSTEM
NORK ORDER- - 06-27-00 NORK BEGAN- 00-00-00 ' '**************************************************'
DATE NORK COMPLETED= TIME COMPUTED- 07-13-00 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *'
CONTRACT WORKING DAYS- 255 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN
WORKING DAYS CHARGED- " 0 PERCENT TIME USED- 0 ' '**************************************************'
M. E. HUNTER & ASSOCIATES, INC.
CONTRACT 05003003 ' TOTALS ' 5,164,424.09' .00' .00' 0.0'
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/295/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.