DISTRICT 03 AS OF JUL 10, 2000 PAGE 45
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
CLAY NR SPUR 510 ' 6.950 ' 6,454,366.90' 1,014,488.85' 1,414,183.33' 23.0'
US 287 NR EAST FORK OF LITTLE WICHITA RV (NB)
0224-01-049
NH 2000(247) 11" CRCP 0/L,HMAC BOND BREAKER L/U
& SET
WORK ORDER- 04-26-00 WORK BEGAN- 05-19-00
DATE WORK COMPLETED- TIME COMPUTED- 05-12-00
* CONTRACT WORKING DAYS- 113 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 31 PERCENT TIME USED- 27
DUININCK BROS, INC.
CONTRACT 03003003 ' TOTALS ' 6,454,366.90' 1,014,488.85' 1,414,183.33' 23.0'
************************************************************************************************************************************
CLAY FM 1288 ' 7.908 1,182,400.34' 6,240.66' 6,240.66' .5'
US 287 NR LITTLE WICHITA RIVER (NBL) ' '
0224-02-037
STP 2000(240)R UNDERSEAL AND OVERLAY
WORK ORDER- 04-17-00 MORK BEGAN- 06-23-00
DATE WORK COMPLETED- TIME COMPUTED- 05-03-00
CONTRACT WORKING DAYS- 39 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 19 PERCENT TIME USED- 49
~~ ,
DUININCK BROS, INC.
CONTRACT 03003020 ' TOTALS ' 1,182,400.34' 6,240.66' 6,240.66' 0.5'
************************************************************************************************************************************
CLAY FM 171 ' 6.443 ' 591,567.35' 538,465.88' 538,465.88' 95.8'
SH 79 OKLAHOMA STATE LINE ' '
0282-02-023
STP 2000(241)R 1 1/2" OVERLAY
WORK ORDER- 04-17-00 MORK BEGAN- 06-12-00
DATE WORK COMPLETED- TIME COMPUTED- 06-01-00
CONTRACT WORKING DAYS- 25 ADDL DAYS GRANTED- 0 ' ' '
WORKING DAYS CHARGED- 19 PERCENT TIME USED- 76
ZACK BURKETT CO. ' '
CONTRACT 03003072 ' TOTALS ' 591,567.35' 538,465.88' 538,465.88' 95.8'
************************************************************************************************************************************
COOKE RED RIVER ' 6.616 ' 260,212.88' 70,653.58' 220,426.67' 88.2'
IH 35 DENTON COUNTY LINE
0194-02-074
IM 35-7(44) RAISING & REPLACING MBGF, ETC.
COOKE RED RIVER ' 15.211 ' 487,226.79' 64,912.89' 337,566.73' 72.1'
IH 35 DENTON CL
0195-01-081
IM 35-7(44) RAISING & REPLACING MBGF, ETC.
WORK ORDER- 03-14-00 WORK BEGAN- 03-27-00
DATE WORK COMPLETED- TIME COMPUTED- 03-30-00
CONTRACT WORKING DAYS- 50 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 33 PERCENT TIME USED- 66
A.S.C. PAVEMENT MARKINGS, INC.
CONTRACT 02003033 ' TOTALS ' 747,439.67' 135,566.47' 557,993.40' 77.7'
COOKE ETC IH 35 US 82' 156.194 ' 1,770,238.62' .00' .00' .0'
FM 372 ETC
0194-03-020 ETC
CPM 194-3-20 SEAL COAT
WORK ORDER- 03-03-00 WORK BEGAN- 00-00-00
,,DATE WORK COMPLETED- TIME COMPUTED- 03-19-00
CONTRACT WORKING DAYS- 33 ADDL DAYS GRANTED- 31
WORKING DAYS CHARGED- 4 PERCENT TIME USED- 6
JOE RICHARDS, INC.
CONTRACT 02003048 ' TOTALS ' 1,770,238.62' .00' .00' 0.0'
************************************************************************************************************************************
COOKE IN GAINESVILLE AT CALIFORNIA ST ' .001 ' 462,613.00' .00' .00' .0'
VA BROADAY ST
0903-15-026
STP 95(333)TE TRANSPORTATION ENHANCEMENT
r~~ ,
WORK ORDER- 03-16-00 WORK BEGAN- 00-00-00
DATE WORK COMPLETED- TIME COMPUTED- 04-01-00
CONTRACT WORKING DAYS- 136 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 62 PERCENT TIME USED- 46
B. J. COMPANY CONTRACTORS, INC.
CONTRACT 02003098 ' TOTALS ' 462,613.00' .00' .00' 0.0'MIS. CIS. 19
MONTHLY STATE LET CONSTRUCTION REPORT
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/53/: accessed June 29, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.