Texas Construction and Maintenance Report: July 2000 Page: PAGE68
508 p. ; 28 cm.View a full description of this report.
Extracted Text
The following text was automatically extracted from the image on this page using optical character recognition software:
DISTRICT 04 AS OF JUL 10, 2000 PAGE 68
**************r********>***************************x*****x***************************************>*************r*************
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
HUTCHINSON SEE PLANS FOR VARIOUS LOCATIONS ' 1.000 ' 121,094.40' 9,047.10' 42,437.10' 35.0'
SH0207 SEE PLANS FOR VARIOUS LOCATIONS
6040-78-001
RMC - 604078001 MOVING RIGHT OF MAY
WORK ORDER- 09-23-99 MORK BEGAN- 09-28-99
DATE WORK COMPLETED- TIME COMPUTED- 10-01-99
CONTRACT WORKING DAYS- 96 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 5 PERCENT TIME USED- 5
BRENT WHITAKER
CONTRACT 06990403 ' TOTALS ' 121,094.40' 9,047.10' 42,437.10' 35.0'
************************************************************************************************************************************
HUTCHINSON SEE PLAN SHEETS ' 1.000 ' 62,500.00' .00' 11,500.00' 18.4'
SH0136 SEE PLAN SHEETS
6036-13-001
RMC - 603613001 LANE BLADING OF ROADWAY SNOW AND/OR
ICE
WORK ORDER- 12-01-98 WORK BEGAN- 12-01-98 ' '**************************************************
DATE WORK COMPLETED- TIME COMPUTED- 12-01-98 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 100 ADDL DAYS GRANTED- 79 ' '* TIME OF THIS RUN
WORKING DAYS CHARGED- 83 PERCENT TIME USED- 46 ' '**************************************************
E. D. BAKER CORPORATION
CONTRACT 10980403 ' TOTALS ' 62,500.00' .00' 11,500.00' 18.4'
************************************************************************************************************************************
MOORE SEE PLANS ' 1.000 ' 7,716.54' .00' 3,755.62' 48.6'
US0087 SEE PLANS
6027-32-001
RMC - 602732001 PICNIC AREA MAINTENANCE
WORK ORDER- 05-28-98 WORK BEGAN- 06-01-98 ' '**************************************************
DATE WORK COMPLETED- TIME COMPUTED- 06-01-98 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 730 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN
WORKING DAYS CHARGED- 330 PERCENT TIME USED- 45 ' '**************************************************
D.C. CONSTRUCTION
CONTRACT 04980403 ' TOTALS ' 7,716.54' .00' 3,755.62' 48.6'
************************************************************************************************************************************
MOORE SEE PLANS FOR VARIOUS LOCATIONS ' 1.000 ' 161,136.00' .00' 30,348.00' 18.8'
US0287 SEE PLANS FOR VARIOUS LOCATIONS
6040-84-001
RMC - 604084001 MOWING HIGHWAY RIGHT OF WAY
WORK ORDER- 10-21-99 WORK BEGAN- 11-01-99
DATE WORK COMPLETED- TIME COMPUTED- 11-01-99
CONTRACT WORKING DAYS- 112 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 9 PERCENT TIME USED- 8
WESTEX MOWING
CONTRACT 06990409 ' TOTALS ' 161,136.00' .00' 30,348.00' 18.8'
************************************************************************************************************************************
MOORE SEE PLANS FOR VARIOUS LOCATIONS ' 1.000 ' 76,891.75' .00' 72,280.25' 94.0'
US0087 SEE PLANS FOR VARIOUS LOCATIONS
6027-85-001
RMC - 602785001 MOWING HIGHWAY RIGHT OF WAY
WORK ORDER- 11-09-98 WORK BEGAN- 11-18-98 ' '**************************************************
DATE WORK COMPLETED- TIME COMPUTED- 11-16-98 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 48 ADDL DAYS GRANTED- 0 ' '* TIME OF THIS RUN
WORKING DAYS CHARGED- 46 PERCENT TIME USED- 96 ' '**************************************************
SQUARE G, INC.
CONTRACT 08980417 ' TOTALS ' 76,891.75' .00' 72,280.25' 94.0'
************************************************************************************************************************************
MOORE SEE PLANS ' .001 ' 16,280.00' 830.00' 4,100.00' 25.1'
US0087 SEE PLANS
6047-88-001
RMC - 604788001 PICNIC AREA MAINT/LITTER
PICKUP/MOWING
WORK ORDER- 12-14-99 WORK BEGAN- 12-22-99
DATE WORK COMPLETED- TIME COMPUTED- 12-22-99
CONTRACT WORKING DAYS- 612 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 155 PERCENT TIME USED- 25
RODRIGUEZ MOWING
CONTRACT 11990401 TOTALS ' 16,280.00' 830.00' 4,100.00' 25.1'
************************************************************************************************************************************MONTHLY LOCAL LET MAINTENANCE REPORT
MIS.CIS.19
Y
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/76/: accessed June 29, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu.; crediting UNT Libraries Government Documents Department.